'˜Advance works' on M27 smart motorway scheme set to begin
On Thursday, March 15, Highways England is due to start advance works, collecting survey information to help design the main route of the smart motorway – which will run from Junction 4 for the M3 to Junction 11 for Fareham.
In an open letter to nearby residents, project manager Deborah Makinde says that a public exhibition will follow on from the survey.
Advertisement
Hide AdAdvertisement
Hide AdShe said: ‘Advance works for this scheme are planned to start on March 15.
‘These advance works will include surveys of the pavements, drainage, ducting and ecology along the route.
‘The survey information will be used to inform the scheme’s detailed design for the main route – with a planned scheme completion of spring 2021.
‘We will be hosting a public information exhibition in late spring 2018.
‘The exhibition will be held along the route – and will be attended by key members of our project team, who will be available to answer any queries attendees may have.’