M27 to be partly closed for bridge demolition next week
The motorway will be shut between junctions 3 and 5 near Romsey and motorists are advised to plan ahead.Â
The M27 will be closed from 10pm on Friday (September 28) to 5am Monday (October 1) for demolition of existing west bridge.Â
Advertisement
Hide AdAdvertisement
Hide AdThe closure of the motorway near Romsey next weekend is the first of three scheduled to take place over the coming 16 months.Â
Highways England project sponsor Andrew Winson said: '˜Our work to replace the Romsey Road bridge over the M27 is a vital part of our work to ensure that the bridges on England's major roads remain operating safely and reliably for the millions of people who depend on them every day.
'˜This bridge will be replaced in three stages over the next 16Â months, with the new bridge being built in the site compound nearby and lifted into place.
'˜By completing the work in this way, we hope to keep overall disruption to an absolute minimum.
Advertisement
Hide AdAdvertisement
Hide Ad'˜We understand that these closures will inevitably cause considerable disruption in the area and we advise that road users plan journeys in advance, especially those heading for the ports.
'˜The M27 carries 140,000 vehicles daily so we are asking drivers to check before they travel and allow extra time for their journey if they can.
'˜We also urge drivers '“ especially those of HGVs or similar heavy and high-sided vehicles '“ to follow the signed diversion routes as these have been chosen as they are the most suitable routes and can cope with heavy flows of traffic.'
Why is the M27 being closed?Â
The 40-year-old bridge is nearing the end of its life and is in need of replacement.
Advertisement
Hide AdAdvertisement
Hide AdThe only safe way to do this is to close the motorway while this takes place.
The Romsey Road Bridge is well used and carries tens of thousands of vehicles daily.
The bridge is actually made up of two individual bridges, both will be closed for three full weekends while the existing bridge is demolished and a new one installed.
The replacement bridge has a different design and will have a lifespan of 120 years.
The weekend closures will take place as follows:
Advertisement
Hide AdAdvertisement
Hide Ad '“ 10pm on Friday, September 28, to 5am Monday, October 1 '“ demolition of existing west bridge
- 10pm on Friday, April 26, 2019 to 5am Monday, April 29, 2019 '“ installation of new bridge
- 10pm on Friday, October 13, 2019, to 5am Monday, October 21, 2019 - demolition of existing east bridge
During the work, the M27 will be closed in both directions between junctions 3 and 4, and the A3057 Romsey Road over the bridge will also be closed.
Advertisement
Hide AdAdvertisement
Hide AdWhen the A3057 reopens on Monday morning, there will be a single lane over the bridge, which will be traffic light controlled.
What are the diversions?Â
During the weekend closures of the M27 the following clearly signed diversions will be in place:
Eastbound:
Traffic on the eastbound M27 will be diverted off the motorway and directed towards Romsey.
High-sided vehicles will be diverted along the A27 through North Baddersley to re-join the M27 at junction 5, avoiding the low bridges in Romsey.
Advertisement
Hide AdAdvertisement
Hide AdVehicles not exceeding the height limit will be diverted along the A3090 to the M3 just south of Winchester.
Westbound:
The westbound M27 will be diverted via the M3, A34, A303, A345, A36 to re-join at junction 2.
The westbound diversion will also be signed from junction 8 on the M3 so that southbound M3 traffic can join the diversion route by using the A303.
There will also be a diversion route for the A3057 (Romsey Road) itself.
Advertisement
Hide AdAdvertisement
Hide AdThis work has been carefully planned and agreed with Hampshire County Council, Southampton City Council, Hampshire Police and other stakeholders.Â
While the motorway is shut, Highways England and its contractors will use the closure to carry out routine maintenance, such as vegetation clearance and drainage work.