Southern Water enters ‘crucial’ phase of £1.7bn project - here’s what they are working on

“We’re leaving no stone unturned.”

Investigations are underway to improve Southern Water’s handling of wastewater and storm overflows - which would benefit thousands of residents.

Southern Water is beginning a £170m programme aimed at reducing storm overflows and improving water quality across Havant, Waterlooville, and Hayling Island. As part of this work, the water company is identifying ways of keeping rainwater out of the wastewater network and reducing the need for storm overflows during heavy rainfall.

The work forms part of the company's wider £1.5bn Clean Rivers and Seas Plan, which aims to reduce storm overflows over the next decade.

Southern Water is undertaking work across Portsmouth and the surrounding area.placeholder image
Southern Water is undertaking work across Portsmouth and the surrounding area. | Southern Water

Southern Water said its work had already helped prevent 117 storm overflows in the Portsmouth catchment since 2025, with further improvements expected as the programme expands.

Possible solutions include sustainable drainage systems, disconnecting surface water from wastewater sewers, sealing pipes to prevent groundwater entering the network and using artificial intelligence to manage flows more effectively.

The investigations will help identify the best combination of measures for each community. Work is already under way in Portsmouth, Gosport and Fareham, where surveys and improvement projects have been carried out.

So far, almost 1.5 hectares of surface water has been removed from residential and commercial properties, with plans to address a further 15.5 hectares through major separation schemes and sustainable drainage projects.

At Tesla Drive in Drayton, 7,000 square metres of impermeable surface area has been removed through 230 metres of new surface water sewer, separating two connections from the wastewater network.

Southern Water has also sealed around 3,000 metres of sewer in Port Solent and Spice Island to reduce tidal water entering the combined network. A further £70m is being invested at Budds Farm Wastewater Treatment Works.

This includes a £20m storm tank, expected to be completed by spring 2027, which will provide additional storage during periods of heavy rainfall.

A separate £50m upgrade programme is due to start early next year and will increase the site's treatment capacity by more than 40 per cent, allowing more wastewater to be treated and helping reduce the use of storm overflows.

Laura Moran, Southern Water's programme delivery lead, said: “This is one of the most ambitious storm overflow reduction programmes we've ever delivered. We're already making strong progress across Portsmouth, and we're now taking that momentum into surrounding communities to help create cleaner rivers, harbours and seas across the wider catchment.

“Right now we're in the crucial investigation phase, leaving no stone unturned as we look at every part of the network to identify where we can make the biggest difference.”

She said the programme would combine new technology with nature-based solutions to deliver long-term environmental benefits.

Southern Water is also encouraging customers to check how their properties are connected to the sewer network.

Where rainwater is entering wastewater pipes, the company says it may be possible to identify opportunities to redirect it into the correct surface water sewer, helping reduce pressure on the system.

The investigations will determine which measures are most suitable for each area before further work is developed.