Part of the North Portsea Island Scheme, the next stage of work will take place along Eastern Road.
It will take place in two phases; the first involving construction of an earth embankment, a steel sheet pile wall and the raising of Eastern Road, adjacent to Kendall’s Wharf.
The second stage will include the construction of a seawall along 2.4km of the Eastern Road, encasing the existing seawall and raising the defence level by approximately 1.2m.
Most Popular
-
1
Woman arrested after little girl, 3, attacked by dog and left with 'life changing injuries' in Leigh Park
-
2
Woman, 44, whose large Dobermann dog mauled girl, 3, on Leigh Park street released back into neighbourhood by police
-
3
Man threatened with machete while washing car and assaulted in Portsmouth with police hunting two men
-
4
WATCH: This is the moment a man with a grudge fire-bombed a family's garden in Leigh Park
-
5
Four people hospitalised after 'serious' multi-vehicle crash involving lorry on A27 near Chichester
Construction on the Kendall’s Wharf section is due to start in September to be completed by April 2020.
Subject to planning approval, work could begin along Eastern Road in April 2020 and is predicted to end late in 2022.
More information on the designs can be viewed here.