The Lido is now at its final level, allowing the team to turn their attentions to preparing the sides of the pool. The team are also working on the filtration system pipework which will all be underground eventually, connecting the water tank, the pool and the plant room.
1. Hilsea Lido
As the base of the pool has had the final concrete pour, the team are now preparing the sides of the pool. The steel work is going in, and then the sides will be concreted too | Portsmouth City Council Photo: Portsmouth City Council
2. Hilsea Lido
The team are working on the filtration system pipework which will all be underground eventually, connecting the water tank, the pool and the plant room | Portsmouth City Council Photo: Portsmouth City Council
3. Hilsea Lido
To concrete the sides the team will need to use this 'shutter', which is a temporary support to hold the wet concrete in place until it hardens and sets. If this wasn't used the concrete wouldn't set in the right shape, but also wouldn't have the strength it needs. | Portsmouth City Council Photo: Portsmouth City Council
4. Hilsea
Concrete that has been poured onto the base of the pool, bringing it to its final level. | Portsmouth City Council Photo: Portsmouth City Council