The southbound carriageway of the Eastern Road has been closed from Burrfields Road to Hayling Avenue since January 4. The water company has provided an update on the repair work with 1,649 metres of the sewer pipe now successfully lined.
Get access to trustworthy local news for a fiver when you sign up for a digital subscription to The News. Support our journalism and get unlimited access to our website. Find out more and sign up today.
A Southern Water spokesperson said: “Work to upgrade the sewer beneath Eastern Road is continuing as part of a £3 million investment to protect one of Portsmouth’s most important routes. So far, we’ve successfully lined 1,649 metres of the sewer pipe. We are currently working on reinstating the road.
“Progress can be affected by factors such as groundwater levels, access to specialist equipment and the time needed for repairs to cure safely underground. We’re working day and night, with much of it taking place below ground and out of sight.”
The spokesperson added: “Work was scheduled to last around eight weeks, subject to conditions, and are going as planned. We fully recognise the impact of the road closure and apologise for the inconvenience. We would like to thank residents and road users for their patience and understanding while these vital works continue.”
.jpeg?crop=4:3&trim=&width=800)
1. Eastern Road closure
One month on from the Eastern Road closure, 1,649 metres of sewer pipe has been successfully lined. | Southern Water

2. Eastern Road closure
The works were expected to take eight weeks to complete. | Southern Water
.jpeg?crop=4:3&trim=&width=800)
3. Eastern Road closure
A lot of the work has taken place below ground with people on site day and night. | Southern Water

4. Eastern Road closure
The Eastern Road remains closed southbound between Burrfields Road and Hayling Avenue. | Southern Water