SGN has confirmed that major lane closures will be in place on London Road, Portsbridge Roundabout and roads approaching the roundabout over two weekends - and this weekend will be the first of the two.
This weekend lane closure will be in place between 7pm today (Friday, February 7) and 5am on Monday, February 10. The second closure will be the following weekend between 7pm on Friday, February 14 and 5am on Monday, February 17.
Advertisement
Hide AdAdvertisement
Hide Ad

As a result of the works being completed, the following lane closures will be in place during both weekends:
- Hilsea dedicated slip lane from the A27/M27 will be closed
- London Road southbound will be down to a single lane
- Portsbridge roundabout lane closures will be in place, with a single lane remaining open
- Bus stops will be temporarily closed within lane closures – it is advised that bus passengers should contact their service providers for the latest update on changes to bus stop locations and timetables. This will include the Donaldson Road bus stop between McDonald's and Portsbridge Roundabout
A spokesperson for SGN said: “To enable the gas main replacement work to progress on London Road and into the verge, we’re planning two weekends of major lane closures on London Road, the Portsbridge roundabout and roads approaching the roundabout.
“We understand these weekend lane closures will be extremely disruptive for road users. However, this will mean we can carry out 24-hour working to move from working in the road to the grass verge next to the Portsbridge South Car Park.
“We will then continue to work along a section of London Road with a single lane closure so we can continue to work safely in this area during this first phase of work in this area in 2025.”
Advertisement
Hide AdAdvertisement
Hide AdThe works are part of phase one of an ongoing SGN gas maintenance project which will see the replacement of 430m of medium-pressure gas main on London Road from Northern Parade to Portsbridge Roundabout.
Phase one of the project started on January 6, 2025 and it will continue until March 31. The second phase of the maintenance works will commence on April 1 and engineers will replace the low-pressure gas pipes on London Road from Northern Parade to Portsbridge Roundabout.
This work will be completed using an insertion method, which will significantly reduce the time to complete this phase.
The ‘disruptive’ lane closures coincides with road closures in front of Cosham Railway Station. The road is set to be closed from 8pm tomorrow (Saturday, February 8) until 8am on Sunday, and then 9pm on Sunday until 4am on the Monday to allow Network Rail to carry out maintenance work on the crossing. Diversions will be in place.